Utility units as part of the Heavy Product Quality Enhancement Project at the refinery, in a consortium (EPC+F )

Project Location: Bandar Abbas
Client: Bandar Abbas Oil Refining Company
Start Date: 2023
Status: In Progress

Construction of a 50 MW renewable wind power plant

Project Location: Khorasan Province
Client: Renewable Energy and Energy Efficiency Organization (SATBA)
Start Date: 2024
Status: In Progress
Contract Duration: 60 months

30-inch crude oil transfer pipeline (PC)

Project Location: Bandar Abbas
Client: Bandar Abbas Oil Refining Company
Start Date: 2021
End Date: 2022
Duration: 16 months

Procurement supply of 14 kilometers of pipeline

Project Location: Bandar Abbas
Client: Bandar Abbas Oil Refining Company
Start Date: 2021
End Date: 2022
Duration: 9 months

Additional operations to increase gasoline and diesel production capacity and enhance product quality

    • Increase Euro 4 gasoline production capacity by 4 million liters per day
    • Upgrade gasoline quality to Euro 4, reaching 12 million liters per day
    • Increase Euro 5 diesel production capacity by 14 million liters per day